Project Manager Exam Practice Questions & Quiz

40 questions / 10 random questions

WBS EVM risk scope procurement and communication
Try a 10-question Project Manager Exam quiz

Random questions, instant feedback, and review for missed questions.

Start quiz →

View recommended Project Manager Exam resources →

Included topics (40 questions)

Q1

Which description of WBS is correct?

Answer: A hierarchical breakdown structure of project work

WBS stands for Work Breakdown Structure and decomposes a project into hierarchical work units.

Q2

Which description of a project scope statement is correct?

Answer: It describes deliverables, acceptance criteria, scope, constraints, assumptions, and related items

A project scope statement becomes a basis for creating the WBS and scope baseline.

Q3

In EVM, what does a CPI below 1 mean?

Answer: Cost efficiency is poor and the project tends toward cost overrun

CPI stands for Cost Performance Index. A value below 1 means actual cost is high relative to earned value.

Q4

Which description of qualitative risk analysis is correct?

Answer: Evaluating risk priority based on probability and impact

Qualitative risk analysis evaluates probability and impact to determine response priorities.

Q5

Which description of contingency reserve is correct?

Answer: Reserve budget or time prepared for identified risks that may occur

Contingency reserve is included in the plan as a response to risks that have been identified in advance.

Q6

Which description of critical chain is correct?

Answer: A concept that considers resource constraints and conflicts in addition to the critical path

Critical chain manages the schedule while considering not only task order but also resource constraints.

Q7

Which description of OBS is correct?

Answer: An organization chart showing which organization is responsible for work decomposed in the WBS

OBS stands for Organization Breakdown Structure and maps work to organizational responsibility.

Q8

In a fixed-price contract, which side generally bears greater risk?

Answer: The supplier side

In a fixed-price contract, if the development scale exceeds assumptions, it is difficult for the supplier to charge additional costs, so supplier risk is greater.

Q9

Which description of a risk register is correct?

Answer: A document that records identified risks and updates analysis and response plans

A risk register is created during risk identification and updated with analysis and response planning results.

Q10

Who is generally responsible for maintaining project governance?

Answer: The project sponsor or project steering committee

Management-level governance that a PM cannot directly control may be handled by a sponsor or steering committee.

Q11

Which description of KGI is correct?

Answer: A quantitative indicator of goals an organization or project should achieve

KGI stands for Key Goal Indicator and defines what metric and level indicate goal achievement.

Q12

Which description is related to ISO/IEC 25010, SQuaRE?

Answer: A standard that defines quality models and quality characteristics for systems and software

ISO/IEC 25010 defines quality models and quality characteristics used for quality requirements and evaluation.

Q13

Which activity is important in stakeholder engagement?

Answer: Identify stakeholders and adjust engagement based on their expectations and influence

In PM, stakeholder identification, analysis, engagement planning, and communication are important.

Q14

What is the role of a Change Control Board, CCB?

Answer: Evaluate change requests and decide approval, rejection, or other handling

A CCB manages changes after considering effects on scope, cost, schedule, and other constraints.

Q15

What is the purpose of issuing an RFP in procurement management?

Answer: To request proposals from candidate vendors and support supplier selection

RFP stands for Request for Proposal and presents requirements to ask vendors for proposals.

Q16

Which is an example of prevention cost in quality cost?

Answer: Costs for reviews and training to prevent defects

Quality costs are often divided into prevention, appraisal, internal failure, and external failure costs.

Q17

What should be clarified in a communication plan?

Answer: Who communicates what, when, and by which method

In PM, clarifying recipients, content, frequency, methods, and responsible persons helps prevent misunderstandings.

Q18

In EVM (Earned Value Management), which describes EV (Earned Value)?

Answer: The budgeted cost of work that has actually been completed

EV is the budgeted value of completed work. Actual cost is AC and planned value is PV.

Q19

When SPI (Schedule Performance Index) is below 1, what does it indicate?

Answer: Progress is behind schedule

SPI = EV/PV; a value below 1 means EV is less than PV, indicating a schedule delay.

Q20

When CPI (Cost Performance Index) is above 1, what does it indicate about cost?

Answer: Work is being done more cost-efficiently than budgeted

CPI = EV/AC; above 1 means EV exceeds AC, indicating cost efficiency better than planned.

Q21

Which description of the critical path is correct?

Answer: The sequence of activities with no slack that determines the total project duration

The critical path is the longest path with zero float; a delay on it delays the whole project.

Q22

Which technique shortens activity duration by adding resources at extra cost?

Answer: Crashing

Crashing adds cost (staff, overtime) to compress duration. Overlapping activities is fast tracking.

Q23

Which technique shortens the schedule by performing normally sequential activities in parallel?

Answer: Fast tracking

Fast tracking overlaps activities to save time but increases the risk of rework.

Q24

Which is an example of the risk response strategy transfer?

Answer: Buying insurance to move the financial impact to a third party

Transfer shifts the impact to a third party (e.g., insurance, contracts), distinct from avoid, mitigate, and accept.

Q25

How is EMV (Expected Monetary Value) calculated in quantitative risk analysis?

Answer: Probability of occurrence multiplied by the monetary impact

EMV is probability times impact; summing EMVs across risks supports decision making.

Q26

In a RACI chart, which letter represents the role that does the work?

Answer: R (Responsible)

R performs the work; A is ultimately accountable. RACI keeps a single A per task.

Q27

Which document records stakeholder interests, influence, and requirements?

Answer: The stakeholder register

The stakeholder register captures identification and assessment results and informs engagement planning.

Q28

Which body reviews change requests to approved baselines and decides to approve or reject them?

Answer: The change control board (CCB)

The CCB formally reviews and decides on change requests, preventing uncontrolled changes.

Q29

What is the gradual, uncontrolled expansion of scope without formal change control called?

Answer: Scope creep

Scope creep is uncontrolled growth of scope; the change control process keeps it in check.

Q30

Which schedule element marks a significant point and has zero duration?

Answer: A milestone

A milestone has zero duration and marks key completion or approval points.

Q31

Which describes the function point method?

Answer: Estimating software size from functional units such as inputs, outputs, and files

Function points measure size by user-visible functionality, making estimates relatively language-independent.

Q32

Which review technique is a formal review where participants take defined roles to find defects early?

Answer: Inspection

Inspection is a formal, role-based review highly effective at finding defects.

Q33

In a firm fixed-price contract, who primarily bears the cost-overrun risk?

Answer: The seller (vendor)

Because the price is fixed, the seller mainly bears cost-overrun risk in a firm fixed-price contract.

Q34

Which correctly distinguishes a risk from an issue?

Answer: A risk is an uncertain future event; an issue is a problem that has already occurred

A risk is an unrealized uncertain event; an issue is a realized problem. A risk that occurs becomes an issue.

Q35

Which activity is the buyer formal confirmation and acceptance that deliverables meet requirements?

Answer: Acceptance (sign-off)

Acceptance confirms deliverables meet acceptance criteria and formally receives them, evidencing scope completion.

Q36

When a change request affects an approved baseline, what should the project manager do first?

Answer: Assess the impact and submit it for approval through the change control process

A baseline-impacting change must be evaluated for scope, cost, schedule, quality, and risk impacts and then handled through formal change control.

Q37

Which engagement strategy is most appropriate for a stakeholder with high power but low interest?

Answer: Keep them satisfied by providing concise, periodic updates on key points

A high-power, low-interest stakeholder should be kept satisfied with concise communication on important matters, without overloading them.

Q38

If a vendor deliverable does not meet contractual acceptance criteria, what is the most appropriate project manager response?

Answer: Record the nonconformance against the contract and acceptance criteria and request correction

Procurement control checks deliverables against the contract, SOW, and acceptance criteria; nonconformances should be recorded and corrected.

Q39

What is the most appropriate purpose of a quality audit?

Answer: To verify whether quality processes follow defined policies and procedures and identify improvements

A quality audit objectively checks process compliance and effectiveness and identifies corrective actions or improvement opportunities.

Q40

Using insurance for a low-probability but high-impact business continuity risk corresponds to which risk response strategy?

Answer: Transfer

Insurance shifts financial impact to a third party, making it a typical risk transfer response for threats.

certdrill.dev is an independent, unofficial learning site and is not affiliated with LPI Japan, IPA, AWS, Microsoft Azure, or any exam provider. Questions and explanations are original content.